    (Rupees in Crores)

    YEAR OF LAUNCH

    :

    December, 2004

    SCHEDULE OF COMPLETION 

    :

    September, 2008

    COST SANCTIONED (till 3/10)

    :

    Rs.  647.86

    FUND RELEASED (till  3/10)

    :

    Rs.  284.76

    FUND UTILISED (till  3/10)

    (Including State Share)

    :

    Rs.  246.02

    FINANCIAL PROGRESS (%)

    :

    37.97%

    NO. OF SCHEMES SANCTIONED

    :

    32

    NO. OF SCHEMES COMPLETED

    :

    14

    STATES COVERED

    :

    3                                                                                                          

    TOWNS COVERED

    :

    15

    RIVERS COVERED

    :

    1

     

     

    JBIC FUNDED PROJECT

    STP CAPACITY SANCTIONED

    :

    189.00 mld

    STP CAPACITY CREATED          

    :

    0.00     mld

     

     