No.J-20012/11/98-IA.II(M)
Government of India
Ministry of Environment & Forests
Paryavaran Bhawan,
CGO Complex, Lodi Road,
New Delhi-110003.
Dated: 28th October 2004
C I R C U L A R
In
modification to the Circular dated 12.02.2004 in regard to the procedure for
obtaining environmental clearance in the case of mining projects under the
Environmental Impact Assessment (EIA) Notification, 1994 and amendments
thereto, the following are to be followed with immediate effect:
I APPLICABILITY
OF EIA NOTIFICATION 1994
The EIA Notification, 1994 as amended from time to
time shall include:
(i) Mining
projects of major mineral with more than 5ha lease area, which have started production or increased their
production and/or lease area on or after 27.01.994.
(ii) In
addition, all mining projects of major minerals of more than 5 ha lease area which have so far not
obtained an environmental clearance under
the EIA Notification, 1994 shall do so at the time of renewal of their lease in the context of the SC Judgement
dated 18.03.2004 in W.P.
4677/1985 – M.C.Mehta vs UOI & Ors.
II ISSUES
PERTAINING TO ROUTING/FORWARDING OF PROPOSAL.
(i) Routing
of proposal through the concerned Central Government/State
Government Department is a must with reference
to the following:
(a)
The projects in respect of which an application is being made to the Ministry of Environment & Forests
for Site/Environmental clearance for the
first time either for new lease area/expansion in lease area and/or production or both or for renewal of lease
area.
(ii) Nodal
Department for routing of applications:
(a)
The nodal Department in the State Government for routing of proposals of private sector companies is
the State Mines and Geology
Department or the Department that controls the Mines & Geology/ Mineral Resources Dept./Division.
(b)
Public Sector Projects should be routed through their respective Ministries in the Central Government.
(iii) The
forwarding letter of the Central Govt. Dept./State
Govt. must clearly indicate the following:
(a)
Name of the proposal.
(b)
Name of the Company.
(c)
Location: village, Taluk/Mandal, District and State.
(d)
Details of lease area and production.
(e)
Details of expansion from .... ha/tpa to ....ha/tpa (if expansion in area and/or in
production).
(iv) If the application involves different
leases of the same company from the same area/region, then a separate
application for each lease has to be made and the forwarding letter should also
preferably be for each separate application. In case, the State Government
forwards the proposals in one composite letter, then the letter must clearly
specify the names of all the leases, their location (village, Taluk, and
District), lease area and production capacity for each of the applications.
(v) Routing of proposal is not required for the following:
(a) If the project has already been accorded
environmental clearance once from
MOEF (after 27.01.1994) and is now again applying for expansion (in lease area and/or production) for
the same project.
(b) IBM/Ministry of Coal’s approval of the
Mining Plan for the total lease area/project area as the case may be has been
obtained even if the application is
being made for the first time.
III Expansion
in Production
The term ‘expansion’ would include increase in
production or lease area or both.
(a) If the
rated capacity given in the Environmental Clearance letter is being exceeded
it would constitute expansion.
(b) The
projects cannot increase production even if they have the IBM/Min. of Coal’s approval for the enhanced
production until environmental clearance is obtained
for the enhanced rated capacity.
(c) If the
annual production of any year from 1994-95 onwards exceeds the annual production of 1993-94 or its preceding
years (even if approved by IBM), it
would constitute expansion.
(d) Expansion
in production beyond the approved capacity however small would constitute a violation and attract
the penal provisions of the Environment
(Protection) Act. Therefore, the proponent should make a suitable calendar plan for obtaining clearance
for the maximum annual production
levels achievable from the project. The EIA-EMP Study should also be prepared keeping this in view. If the
production increases/is proposed to increase
beyond what was submitted in the EIA-EMP report for which an environmental clearance was obtained/applied for, then it would constitute expansion.
IV ISSUES
PERTAINING TO PUBLIC HEARING
Public Hearing for all mining projects, which attract the
provisions of the EIA Notification, 1994 as amended from time to time.
However, in view of the various queries received from time to time, it is
clarified that Public Hearing is a pre-requisite for the following projects:
(i) If the
proposal is a new one.
(ii) If
a pre-1994 project is being submitted for environmental clearance to MOEF for
the first time for proposed expansion in production and or lease area.
(iii) If
a project had obtained an environmental clearance between
1994-1997 (prior to introduction of Public Hearing), and is now applying
for environmental clearance for expansion in lease area and/or production.
(vi) If a project had obtained environmental clearance
after 10.09.1997 (after the notification on Public Hearing) and has had Public
Hearing already for the original lease area, but is now applying for
environmental clearance for expansion in lease area.
(v) If
a project had obtained environmental clearance after 10.09.1997 (after the
notification on Public Hearing) and has already had Public Hearing on the
proposal and is now applying for expansion in production only.
V ISSUES
PERTAINING TO EIA-EMP REPORT
(a) EIA-EMP
Report based on data that is more than 3 years old shall not be accepted by the MOEF.
(b) The
EIA-EMP Report in the cover as well as in the Introduction para must clearly
state the rated capacity and the period for which the study has been made.
(c) Environmental
clearance will be valid only for the rated capacity for which the EIA-EMP Report has been prepared even if
the project has IBM approval for a higher
rated capacity/production.
(d) If
the proponent has already obtained an environmental clearance after 27.01.1994 and has applied again for
increase in production and/or lease area
within 5 years from date of obtaining environmental clearance, then a Supplementary EIA-EMP Report incorporating the
essential issues should be submitted
to MOEF while making the application in the relevant form and questionnaire along with NOC and Public Hearing
and IBM approval for the proposed
expansion. A copy of the original EIA-EMP Report would be required to be submitted for the
appraisal.
(e) If
there are several mining leases in the same area located contiguous or adjacent to each other or at a distance from
each other, the EIA-EMP Report should be
prepared for the baseline data of the lease area (core zone) and 10km study area (buffer zone) around
each mine separately for each mine.
VI (a) All Mining Plans/Renewal of
Mining Schemes close to the last year of the Plan/Scheme
period would require to submit the IBM Approval of
their renewal for the next 5-year
Period while submitting their application for environmental
clearance. As Ministry of Coal is approving
Mine Plan for the entire life of the
mine, the approved calendar plan for annual production for the life of the mine should be submitted.
(b) If
the project after grant of environmental clearance, obtains approval for Mining
Plan/renewal of Mining Scheme for a rated capacity higher than that for which
the Environmental clearance was granted, a fresh application in accordance with
the procedure specified in the EIA Notification should be submitted for
obtaining environmental clearance for the higher rated capacity.
(R.CHANDRAMOHAN)
Joint
Secretary to the Government of India
To
1. All
State Governments (Department of Mines & Geology, Dept. of Environment
& Forests)
2. All
State Pollution Control Boards
3. FIMI
and other Mine Associations
4. Ministry
of Coal & Mines: Department of Coal, Department of Mines
5. Indian
Bureau of Mines and Coal India Limited
6. MOEF
Regional Offices
* * *
AMENDMENT TO NOTIFICATION ON PUBLIC HEARING DT. 10.09.1997
ON
PUBLIC HEARING: Presently, there is no provision in the P.H. Notification
for reconduct of P.H. There is also no time limit prescribed thereunder for its
validity. An amendment to the EIA Notification on P.H. is reqd. specifying that
the validity for submission of a P.H. for obtaining environmental clearance is
for a maximum period of 5 years only. The amendment will cover the following
issues:
Fresh conduct of Public hearing is
required w.r.t the following:
(i) If
the proposal was received in the MOEF beyond 5 years time limit from the date of conduct of P.H.
(ii) Application
was received in the MOEF but the file was closed/returned back to proponent/rejected due to any
reason (may or may not in reference to
P.H.) and 5 years had elapsed since the
conduct of P.H.
(iii) Project
was not taken up by the PP even 5 years after the issuance of the environmental clearance.
(iv) The EIA-EMP Report submitted by the
Proponent required extensive revision/resubmission.
Summary Report of the revised EIA-EMP report would
require to be placed in a P.H. conducted afresh as a result of changes/modifications made to the EIA-EMP
Report indicates change in impacts.